Swimming pools

Rotorua Aquatic Centre - 50 mtr Outdoor Pool

Project:

To repair and paint the swimming pools and spas

Specified System:

This pool forms part of the local public swimming facility and as such is run on a strict 24 / 7 programme. Generally it is closed at three yearly intervals for a complete coatings makeover. The recoat window is only two weeks long and normally occurs in the Winter months.

The recoat specification includes for a controlled hydroblast preparation standard followed by the application of a Chlorinated Polymer coating system.